Data Center Civil Engineering

A guide to the civil site engineering behind data center development, and to the reading RSP Engineers has published on it.

What data center civil engineering covers

Data center civil engineering is the site work that lets a facility be built, powered, cooled, drained, reached and expanded: feasibility and due diligence, grading and earthwork, stormwater and flood risk, utilities and corridors, permitting and construction administration. This page organizes what RSP Engineers has published on each of those subjects and states plainly what RSP does on these sites.

The pathways below are the order in which the civil questions are usually asked on a project. Each leads to a page that explains the buyer problem, states RSP's scope and lists the articles on that subject.

The pathways

What RSP Engineers does on these sites

RSP's scope is the civil site engineering:

  • Site feasibility and due diligence, and the geotechnical program that supports them.
  • Grading and earthwork design, from finished floor elevations to compaction specifications.
  • Stormwater, drainage and flood-risk design for high-impervious, operationally critical sites.
  • Water, wastewater and utility infrastructure design, corridor planning and utility coordination.
  • Permitting strategy, agency coordination and construction administration through closeout.
  • Campus planning and phasing, site layout, access and pavement, and the civil side of physical security.

Scope boundaries

RSP Engineers performs the civil site engineering described above and also provides mechanical, electrical and plumbing engineering through its own licensed staff. Where a project uses both, the interfaces between building systems and site infrastructure are designed together. Structural engineering and the other project disciplines deliver their own scopes, and how a completed facility performs — its energy use, the redundancy of its systems, its availability in service — depends on the owner's requirements, the equipment selected, the serving utilities, the construction and how the facility is operated. It is not determined by any single discipline's design.

Related reading

The 26 articles RSP Engineers has published on this subject, grouped by question. Titles are as published.

Starting points

Campus planning and phasing

Access, pavement and security

Related services

Discuss a site

If you are evaluating or developing a data center site, tell us about the project and we will come back to you about the civil scope.