Third Cycle sewer system evaluation surveys for three 7-Eleven stores in Miami-Dade County

RSP Engineers carried out Third Cycle Sewer System Evaluation Surveys on the private sanitary sewer systems serving three 7-Eleven stores in Miami-Dade County. Each system was inspected, smoke tested and recorded on a sealed SSCS drawing, and DERM found all three in compliance with Chapter 24 in 2026.

Location
Miami-Dade County, Florida
Client
7-Eleven, Inc.
RSP role
Engineer of record for the Sewer System Evaluation Survey: inspection, smoke testing, reporting and the sealed SSCS drawings
Sanitary sewer collection system plan for a convenience store site, showing the wet well and sewer lift station, the grease trap, cleanouts CO1 and CO3 to CO9, and the length and diameter of each gravity sewer segment.

What the project was

Three 7-Eleven stores in Miami-Dade County, one in Cutler Bay and two in Miami, each operate a private sanitary sewer system that discharges into the county's wastewater collection and transmission system through a small pump station. Under Chapter 24 of the Miami-Dade County Code every such system, whether a utility owns it or not, has to be evaluated on a recurring ten-year cycle, with the findings submitted to the Department of Environmental Resources Management for review and approval. RSP Engineers was the engineer of record for the Third Cycle Sewer System Evaluation Survey at all three.

The survey is not a formality. An SSES exists to find and correct excessive infiltration and inflow, meaning groundwater entering through defects and stormwater entering through openings that should not be there, and Chapter 24 sets the limit at less than 5,000 gallons per inch of pipe diameter per day per mile of pipe and laterals. Finding those defects keeps sewage out of the ground, reduces wear on the pump station and lowers what it costs to run.

Why the deadline matters

The consequence of letting an SSES lapse is not a fine, it is a hold on growth. Section 24-42.3(3) prevents new sewage flows being authorised for a sanitary sewer basin, pump station or system until the reports Chapter 24 requires have been completed on schedule. For a retail operator that means a non-compliant permit can sit between a site and its certificate of occupancy, or between a remodel and the extra capacity it needs. It is the kind of problem that gets discovered at the worst possible moment, when the construction is finished and the opening date is already set.

The fieldwork also has a narrow window. Flow testing has to be carried out between 1 June and 30 November of the same calendar year, the wet season, and where the groundwater level is tidally influenced, which in coastal Miami-Dade is a great deal of the county, testing has to happen within two hours of local high tide. Miss the season and the survey waits a year.

What the work involved

Each of the three systems is small, and none of them contains a single manhole. They are short runs of 4-inch PVC between cleanouts, falling to a wet well with two submersible pumps. Across the three sites the survey covered 541.8 feet of gravity sewer. What these systems lack in length they make up in exposure, because a lift station in a parking lot gets walked over, driven over and pressure washed, and its lid is the most likely inflow path in the whole system.

The surveys were built around visual inspection and smoke testing rather than camera work. On a system with no manholes and a few hundred feet of 4-inch pipe, smoke introduced at the wet well reaches every branch, and anywhere it surfaces that is not a vent is a defect. Each system was inspected, every cleanout was opened and graded, the pump station and its cover were examined, and DERM was notified in advance of the tests that require notice. Five smoke tests were carried out across the three stores between March and July 2026 using a plumbing smoke tester with liquid smoke, in dry weather with no precipitation recorded at the time of testing. At one store the grease interceptor line was smoke tested separately from the sanitary collection system, because a grease interceptor sits on its own branch and one injection point does not prove both.

Flow testing was not required at any of the three systems. Each survey closed with an updated Sanitary Sewer Collection System drawing, signed, sealed and dated by a professional engineer licensed in Florida, which Section 24-15.2 requires for the report and the drawings alike.

What the testing found

Two of the three stores needed a repair, and in both cases it was the lift station lid. At the Cutler Bay store the lid was found loose with smoke escaping from it during the first test. It was sealed on 16 April 2026 and the system re-tested on 5 June, when smoke emerged from the lid as designed and nowhere from the ground beside the building. At the Bird Road store the same finding came out of the March test and was corrected on site the same day; the second smoke test in July showed smoke leaving through the sanitary vent system as expected, and no emissions from the ground, the building foundation, the cleanouts or anywhere else that would indicate infiltration, inflow, a cross connection or a structural defect.

The Cutler Bay store also had a leak inside the wet well. It was identified during the inspection and corrected while the crew was on site, rather than written up and scheduled as a follow-up.

The third store, on NW 72 Avenue, passed at the first attempt: cleanouts in good condition, the gravity system operating normally, no smoke along the sanitary sewer line and no repairs required.

Approvals

DERM's Water and Wastewater Division reviewed each submittal against the Chapter 24 requirements and found all three systems in compliance with the Third Cycle SSES code requirements: PSO-0393 on 16 June 2026, PSO-0611 on 7 July 2026 and PSO-0388 on 23 July 2026. The Fourth Cycle reports for all three permits fall due on 12 November 2032.

The outcome

Three permits that each carried an open compliance obligation now carry an approval letter instead, and the two defects the surveys found were repaired during the survey rather than deferred to a second submittal. The practical result for the operator is that none of the three stations is sitting in the way of a future connection, a remodel or a certificate of occupancy.

For anyone responsible for a portfolio of small commercial sites, the useful observation is that these systems are easy to forget precisely because they are small. A private lift station behind a convenience store has no dedicated operator, and the obligation attaches to the permit rather than to the building, so it survives a change of tenant, manager or facilities contractor. The cheap version of this work is the one done inside the wet season with the defects fixed on the day they are found. The expensive version is the one discovered when a permit is suddenly needed in a hurry.

Project facts

  • Three private sanitary sewer systems serving 7-Eleven stores in Miami-Dade County were evaluated under the Third Cycle SSES requirement of Chapter 24 of the Miami-Dade County Code.
  • All three were Plan A surveys, submitted with Sanitary Sewer Collection System drawings signed, sealed and dated by a professional engineer licensed in Florida, as Section 24-15.2 requires.
  • DERM's Water and Wastewater Division found all three systems in compliance with the Third Cycle SSES code requirements: PSO-0393 on 16 June 2026, PSO-0611 on 7 July 2026 and PSO-0388 on 23 July 2026.
  • 541.8 feet of 4-inch PVC gravity sewer was surveyed across the three sites, none of which contains a manhole.
  • Each site is served by a private pump station with two submersible pumps.
  • Five smoke tests were carried out across the three systems between March and July 2026, using a plumbing smoke tester with liquid smoke.
  • Flow testing was not required at any of the three systems.
  • At two of the three stores the lift station lid was found to need sealing against infiltration; both were repaired and the systems re-tested.
  • A leak inside the wet well at the Cutler Bay store was identified during the inspection and corrected on site.
  • The Fourth Cycle SSES reports for all three permits are due on 12 November 2032.
Facilities surveyed
Three: one in Cutler Bay, two in MiamiApproved SSES Third Cycle reports and DERM compliance letters, 2026
DERM permits
PSO-0393, PSO-0388, PSO-0611Approved SSES Third Cycle reports and DERM compliance letters, 2026
Survey type
Third Cycle SSES, Plan AApproved SSES Third Cycle reports and DERM compliance letters, 2026
Gravity sewer surveyed
541.8 ft of 4-inch PVC across three sitesApproved SSES Third Cycle reports and DERM compliance letters, 2026
Manholes
None; cleanout and pump station systemsApproved SSES Third Cycle reports and DERM compliance letters, 2026
Private pump stations
Three, each with two submersible pumpsApproved SSES Third Cycle reports and DERM compliance letters, 2026
Pump capacity
3.15 L/s (about 50 gpm) at two sites, 6.0 L/s (about 95 gpm) at the thirdApproved SSES Third Cycle reports and DERM compliance letters, 2026
Smoke tests
Five across the three systemsApproved SSES Third Cycle reports and DERM compliance letters, 2026
Flow testing
Not required at any of the three systemsApproved SSES Third Cycle reports and DERM compliance letters, 2026
Code limit on infiltration and inflow
Under 5,000 gallons per inch of pipe diameter per day per mileApproved SSES Third Cycle reports and DERM compliance letters, 2026
Repairs
Lift station lids sealed at two sites; wet well leak corrected on site at oneApproved SSES Third Cycle reports and DERM compliance letters, 2026
DERM determinations
In compliance: 16 June, 7 July and 23 July 2026Approved SSES Third Cycle reports and DERM compliance letters, 2026
Next cycle due
Fourth Cycle reports, 12 November 2032Approved SSES Third Cycle reports and DERM compliance letters, 2026

Questions a similar project raises

What is a Sewer System Evaluation Survey (SSES)?

An engineering investigation of a sanitary sewer collection system to find and correct excessive infiltration and inflow. It combines visual inspection of the pipes, cleanouts, manholes and pump station with testing to locate defects, illegal connections and places where stormwater or groundwater is getting in. The point is to keep the system working as designed, prevent sanitary sewer overflows and avoid pumping water that was never meant to be in the sewer.

Who has to carry one out in Miami-Dade County, and how often?

Under Section 24-42.2(3)(a) of the Miami-Dade County Code, every sanitary sewer collection system that is owned or operated by a utility or a non-utility has to be evaluated, with a report submitted to DERM for review and approval. Reports are due on each ten-year anniversary of 12 November 2002, so the obligation applies to private commercial systems with a PSO permit, not only to municipal networks. Each of the three permits in this project now has its Fourth Cycle report due on 12 November 2032.

What happens if a facility misses its SSES deadline?

Section 24-42.3(3) blocks the authorisation of new sewage flows for the basin, pump station or system until the required reports have been completed on schedule. In practice that can stand between a property and a certificate of occupancy, a certificate of use or the additional capacity a remodel or expansion needs. The cost of a lapsed survey is usually a delay to something else rather than a penalty.

Does an SSES always need a camera inspection?

No. The methods are chosen to suit the system. On a large municipal network, robotic CCTV inspection and flow monitoring usually earn their place. On a small private system like these three, a few hundred feet of 4-inch pipe between cleanouts with no manholes, smoke introduced at the wet well travels the whole system, and visual inspection plus smoke testing answers the question. Flow testing was not required at any of these three sites.

When can the testing be done?

Flow testing for an SSES has to be carried out between 1 June and 30 November of the same calendar year, which is the wet season, unless the Director approves otherwise in writing. Where the groundwater level is tidally influenced, the testing has to be done within two hours of local high tide. That window is worth planning around, because missing it can put a survey back by a year.

What do you need in order to quote an SSES?

The PSO permit number, the address, and whatever record drawings exist of the private sewer system, including whether there is a grease interceptor and whether the site pumps or falls to gravity sewer. If the previous cycle report exists, that is the single most useful document, because it establishes what the system looked like last time and what was outstanding.

water and sewer design

civil

Utility Infrastructure Design

RSP Engineers designs utility infrastructure, including water and sewer systems, for reliable project outcomes.

Explore service
Grocery-anchored retail center with parking and landscaping seen from the roadway

Market

Engineering for Retail Development

RSP Engineers specializes in retail development, encompassing site design and permitting for shopping centers and individual stores to optimize business growth.

See how we help
Proposed sewer main profile drawing showing manholes, pipe runs and grades

Market

Engineering for Sewer Infrastructure

RSP Engineers provides sewer force mains, gravity pipes, and pump stations for reliable wastewater collection, protecting public health and the environment.

See how we help
Gas station with fuel canopy and convenience store on a commercial corner lot

Market

Commercial Property Civil Engineering

RSP Engineers provides full-site development for your commercial needs, including restaurants, gas stations, and office buildings.

See how we help

Have a similar project?

Tell us about the site, schedule and jurisdiction and we will outline an approach.