Third Cycle Sanitary Sewer Evaluation Survey (SSES)
RSP Engineers conducts sanitary and storm sewer camera inspections for thorough infrastructure assessments.
Explore serviceCase study · Engineering for Retail Development
RSP Engineers carried out Third Cycle Sewer System Evaluation Surveys on the private sanitary sewer systems serving three 7-Eleven stores in Miami-Dade County. Each system was inspected, smoke tested and recorded on a sealed SSCS drawing, and DERM found all three in compliance with Chapter 24 in 2026.

Three 7-Eleven stores in Miami-Dade County, one in Cutler Bay and two in Miami, each operate a private sanitary sewer system that discharges into the county's wastewater collection and transmission system through a small pump station. Under Chapter 24 of the Miami-Dade County Code every such system, whether a utility owns it or not, has to be evaluated on a recurring ten-year cycle, with the findings submitted to the Department of Environmental Resources Management for review and approval. RSP Engineers was the engineer of record for the Third Cycle Sewer System Evaluation Survey at all three.
The survey is not a formality. An SSES exists to find and correct excessive infiltration and inflow, meaning groundwater entering through defects and stormwater entering through openings that should not be there, and Chapter 24 sets the limit at less than 5,000 gallons per inch of pipe diameter per day per mile of pipe and laterals. Finding those defects keeps sewage out of the ground, reduces wear on the pump station and lowers what it costs to run.
The consequence of letting an SSES lapse is not a fine, it is a hold on growth. Section 24-42.3(3) prevents new sewage flows being authorised for a sanitary sewer basin, pump station or system until the reports Chapter 24 requires have been completed on schedule. For a retail operator that means a non-compliant permit can sit between a site and its certificate of occupancy, or between a remodel and the extra capacity it needs. It is the kind of problem that gets discovered at the worst possible moment, when the construction is finished and the opening date is already set.
The fieldwork also has a narrow window. Flow testing has to be carried out between 1 June and 30 November of the same calendar year, the wet season, and where the groundwater level is tidally influenced, which in coastal Miami-Dade is a great deal of the county, testing has to happen within two hours of local high tide. Miss the season and the survey waits a year.
Each of the three systems is small, and none of them contains a single manhole. They are short runs of 4-inch PVC between cleanouts, falling to a wet well with two submersible pumps. Across the three sites the survey covered 541.8 feet of gravity sewer. What these systems lack in length they make up in exposure, because a lift station in a parking lot gets walked over, driven over and pressure washed, and its lid is the most likely inflow path in the whole system.
The surveys were built around visual inspection and smoke testing rather than camera work. On a system with no manholes and a few hundred feet of 4-inch pipe, smoke introduced at the wet well reaches every branch, and anywhere it surfaces that is not a vent is a defect. Each system was inspected, every cleanout was opened and graded, the pump station and its cover were examined, and DERM was notified in advance of the tests that require notice. Five smoke tests were carried out across the three stores between March and July 2026 using a plumbing smoke tester with liquid smoke, in dry weather with no precipitation recorded at the time of testing. At one store the grease interceptor line was smoke tested separately from the sanitary collection system, because a grease interceptor sits on its own branch and one injection point does not prove both.
Flow testing was not required at any of the three systems. Each survey closed with an updated Sanitary Sewer Collection System drawing, signed, sealed and dated by a professional engineer licensed in Florida, which Section 24-15.2 requires for the report and the drawings alike.
Two of the three stores needed a repair, and in both cases it was the lift station lid. At the Cutler Bay store the lid was found loose with smoke escaping from it during the first test. It was sealed on 16 April 2026 and the system re-tested on 5 June, when smoke emerged from the lid as designed and nowhere from the ground beside the building. At the Bird Road store the same finding came out of the March test and was corrected on site the same day; the second smoke test in July showed smoke leaving through the sanitary vent system as expected, and no emissions from the ground, the building foundation, the cleanouts or anywhere else that would indicate infiltration, inflow, a cross connection or a structural defect.
The Cutler Bay store also had a leak inside the wet well. It was identified during the inspection and corrected while the crew was on site, rather than written up and scheduled as a follow-up.
The third store, on NW 72 Avenue, passed at the first attempt: cleanouts in good condition, the gravity system operating normally, no smoke along the sanitary sewer line and no repairs required.
DERM's Water and Wastewater Division reviewed each submittal against the Chapter 24 requirements and found all three systems in compliance with the Third Cycle SSES code requirements: PSO-0393 on 16 June 2026, PSO-0611 on 7 July 2026 and PSO-0388 on 23 July 2026. The Fourth Cycle reports for all three permits fall due on 12 November 2032.
Three permits that each carried an open compliance obligation now carry an approval letter instead, and the two defects the surveys found were repaired during the survey rather than deferred to a second submittal. The practical result for the operator is that none of the three stations is sitting in the way of a future connection, a remodel or a certificate of occupancy.
For anyone responsible for a portfolio of small commercial sites, the useful observation is that these systems are easy to forget precisely because they are small. A private lift station behind a convenience store has no dedicated operator, and the obligation attaches to the permit rather than to the building, so it survives a change of tenant, manager or facilities contractor. The cheap version of this work is the one done inside the wet season with the defects fixed on the day they are found. The expensive version is the one discovered when a permit is suddenly needed in a hurry.
An engineering investigation of a sanitary sewer collection system to find and correct excessive infiltration and inflow. It combines visual inspection of the pipes, cleanouts, manholes and pump station with testing to locate defects, illegal connections and places where stormwater or groundwater is getting in. The point is to keep the system working as designed, prevent sanitary sewer overflows and avoid pumping water that was never meant to be in the sewer.
Under Section 24-42.2(3)(a) of the Miami-Dade County Code, every sanitary sewer collection system that is owned or operated by a utility or a non-utility has to be evaluated, with a report submitted to DERM for review and approval. Reports are due on each ten-year anniversary of 12 November 2002, so the obligation applies to private commercial systems with a PSO permit, not only to municipal networks. Each of the three permits in this project now has its Fourth Cycle report due on 12 November 2032.
Section 24-42.3(3) blocks the authorisation of new sewage flows for the basin, pump station or system until the required reports have been completed on schedule. In practice that can stand between a property and a certificate of occupancy, a certificate of use or the additional capacity a remodel or expansion needs. The cost of a lapsed survey is usually a delay to something else rather than a penalty.
No. The methods are chosen to suit the system. On a large municipal network, robotic CCTV inspection and flow monitoring usually earn their place. On a small private system like these three, a few hundred feet of 4-inch pipe between cleanouts with no manholes, smoke introduced at the wet well travels the whole system, and visual inspection plus smoke testing answers the question. Flow testing was not required at any of these three sites.
Flow testing for an SSES has to be carried out between 1 June and 30 November of the same calendar year, which is the wet season, unless the Director approves otherwise in writing. Where the groundwater level is tidally influenced, the testing has to be done within two hours of local high tide. That window is worth planning around, because missing it can put a survey back by a year.
The PSO permit number, the address, and whatever record drawings exist of the private sewer system, including whether there is a grease interceptor and whether the site pumps or falls to gravity sewer. If the previous cycle report exists, that is the single most useful document, because it establishes what the system looked like last time and what was outstanding.

civil
RSP Engineers conducts sanitary and storm sewer camera inspections for thorough infrastructure assessments.
Explore service
civil
RSP Engineers designs utility infrastructure, including water and sewer systems, for reliable project outcomes.
Explore service
civil · environmental
RSP Engineers offers civil and environmental engineering services for sustainable project solutions.
Explore service
Market
RSP Engineers specializes in retail development, encompassing site design and permitting for shopping centers and individual stores to optimize business growth.
See how we help
Market
RSP Engineers provides sewer force mains, gravity pipes, and pump stations for reliable wastewater collection, protecting public health and the environment.
See how we help
Market
RSP Engineers provides full-site development for your commercial needs, including restaurants, gas stations, and office buildings.
See how we helpTell us about the site, schedule and jurisdiction and we will outline an approach.