
civil
Storm Drainage Design
Expert stormwater design by RSP Engineers ensures effective drainage and management for your project.
Explore serviceCase study · Engineering for Stormwater Management
An occupied senior living campus in Frisco had drainage that no longer performed as designed. RSP assessed existing conditions, researched the permit record, modelled the stormwater system and designed a collection and regrading scheme approved for construction by the City of Frisco.
Client and site identifiers are withheld under a confidentiality agreement; the scope, role and outcomes described are documented in the project record.

An existing senior living community in Frisco, in the northern Dallas–Fort Worth metroplex, had a drainage system that was no longer behaving the way its original design intended. RSP Engineers was engaged to find out why, and to produce a set of stormwater improvement drawings the City of Frisco could review.
This was not a greenfield site. The campus was built, occupied and landscaped, with residents in place, parking in daily use and a network of water, sewer and storm utilities already in the ground. Everything proposed had to work around that. The scope ran from investigation through to a complete plan set: an assessment of existing drainage conditions, research into the permit record, drainage calculations, hydrologic and hydraulic modelling of the stormwater system, coordination of an independent geotechnical investigation of subsurface soil conditions, and a design addressing the deficiencies that work identified.
RSP acted as the civil engineer of record for the stormwater improvements. The resulting set runs to seventeen sheets and includes existing composite utility plans, paving and grading plans, drainage plans, drainage and structure details, profiles and cross-sections, demolition plans, and the City of Frisco's own standard notes and details.
The difficulty on this site was not the rainfall. It was that the drainage system already existed, was partly undocumented, and sat on top of other buried infrastructure that could not be moved.
Three things made it awkward. First, the site's stormwater depends on an existing retention area with a bank running from elevation 652 feet at the top down to 642 feet at the bottom — a ten-foot drop that any new grading had to respect rather than disturb, alongside an existing detention pond held under a drainage and detention pond easement. Second, the campus is crossed by an easement carrying a drainage and floodway designation, which constrains what can be built and where. Third, the existing utility network was dense and only partly recorded: the composite utility plans document existing stormwater lines in 12-inch PVC, 18-inch PVC and 42-inch reinforced concrete, threaded among water and sewer mains whose depths the drawings explicitly instruct the contractor to field verify, because the proposed storm runs pass close enough that the top of the new storm pipe and the bottom of the existing water and sewer lines are a recorded point of conflict.
That combination is what turns a routine drainage repair into an engineering problem. A new inlet cannot simply be placed where the ponding is worst; it has to be placed where there is room between an existing water main, an existing sewer and a 42-inch storm trunk, at a depth that still drains, on a slope the receiving system can accept, without cutting into a floodway easement or destabilising a ten-foot retention bank.
The investigation came first. RSP assessed the existing drainage condition on the ground, researched the permit record for what had been approved historically, and used that to build a picture of how the system was supposed to work against how it actually behaved. Drainage calculations and hydrologic and hydraulic modelling of the stormwater network followed, which is what converts "it ponds near the parking" into a located, quantified deficiency with a hydraulic cause. An independent geotechnical investigation was commissioned and coordinated, so that subsurface soil conditions informed the grading and structure work rather than being assumed.
The design that came out of it is a collection system rather than a single intervention. Fourteen new structures were laid out — six catch basins and eight curb inlets — and connected by a storm network sized run by run, with pipe diameters from 8 inches up to 64 inches in PVC and HDPE depending on the contributing area and the available cover. The storm pipe schedule works through each leg individually, including the short connections such as the 8-inch HDPE run of 29 linear feet at a 1.0 percent slope that picks up a localised low point.
Grading was handled with berms rather than wholesale regrading, because the campus is occupied and its finished surfaces largely stay. The plans set out three-foot-wide berms at specified elevations across the site — top of berm at 661.00 against a bottom of 660.00 in one location, 665.50 over 664.50 in another, 667.687 over 666.687, 668.68 over 667.68, and 670.00 over 669.00 — each one a one-foot rise placed to redirect sheet flow toward the new inlets instead of toward buildings and paving. A four-foot wall was added where a level change was needed in a position a berm could not occupy.
A substantial part of the work is repair and reconnection rather than new build. The drawings call for an existing stormwater drain manhole to be removed and replaced with a proposed inlet, an existing catch basin to be replaced and reconnected to the new network, and existing inlets to be cleaned. That last item matters more than it sounds: part of what degrades an older system is simply that structures silt up, and a deficiency assessment has to separate a system that is undersized from one that is blocked, because the fixes are not the same.
The set also carries demolition plans, which on an occupied campus are not a formality. Removing a manhole, taking out a catch basin and cutting into live paving all have to happen in an order that leaves the site drained and passable between stages, because residents, deliveries and emergency access continue throughout. Separating demolition onto its own sheets lets the sequence be read independently of the proposed work, which is what a contractor pricing phased construction actually needs.
Profiles and cross-sections were drawn along two section lines so the proposed surface can be read directly against existing grade. On a site where the design intent is a one-foot berm here and a matched elevation there, a plan view alone does not show whether the result drains; the sections are where the relationship between proposed and existing ground becomes checkable, by the engineer and by the reviewer.
The City of Frisco is the reviewing authority. The plan set carries a dedicated sheet of City of Frisco general notes and a sheet of City of Frisco standard details, which is the practical shape municipal review takes in this part of Texas: the city's own construction standards are incorporated into the drawings rather than referenced, so a reviewer can check the proposal against the standard on the same sheet.
Because the work sits near a drainage and floodway easement and modifies an existing detention and retention system, the review is concerned with more than pipe sizing. It is concerned with whether the existing detention function is preserved, whether the changes alter flow leaving the site, and whether anything encroaches on the easements. That is why the existing conditions work and the permit records research are not preliminaries — they are the evidence the review depends on.
Work of this kind on an occupied site also carries a construction-phase dimension that the drawings address directly: the contractor is instructed to protect existing infrastructure along the retention area, to maintain natural grade elevation where equipment is placed over existing utilities, and to connect existing pipe at matching invert elevations rather than re-grading to suit.
The stormwater improvement design was approved for construction by the City of Frisco on 24 April 2025. For an occupied campus that is the point at which the investigation work pays off: the approval covers a scheme that keeps the existing detention and retention function intact, routes new storm runs around utilities that stay in place, and reshapes surface flow with berms rather than regrading a site that residents live on.
The constraints are fixed before you start. Buildings, paving, landscaping and buried utilities are already in place and generally stay, so the design has to find room between them rather than setting out the arrangement from scratch. On this campus the proposed storm runs pass close enough to existing water and sewer that depth conflicts are recorded on the drawings for the contractor to verify in the field.
Usually for one of three reasons, and they need different fixes. The system may be undersized for the way the site now drains, it may be blocked or silted so that capacity exists on paper but not in practice, or the surface grading may have changed so water no longer reaches the inlets. Telling them apart is what a condition assessment and hydraulic model are for.
Review by the City of Frisco against its own construction standards, which are incorporated into the plan set as city general notes and standard details. Where work sits near a drainage or floodway easement or alters an existing detention system, the review also examines whether detention function and off-site flows are preserved.
Because the original approvals state what the drainage system was designed to do, which is the benchmark for judging how it behaves now. Without that record a deficiency assessment is guesswork about intent, and a reviewing agency has no basis on which to compare the proposal against what it approved previously.
Any record drawings or approved plans for the original development, the permit history, a current survey, and a description of where and when water actually causes problems. Photographs during or shortly after rainfall are more useful than most clients expect, because they show where water goes rather than where it was intended to go.

civil
Expert stormwater design by RSP Engineers ensures effective drainage and management for your project.
Explore service
civil · environmental
RSP Engineers offers civil and environmental engineering services for sustainable project solutions.
Explore service
civil
RSP Engineers designs utility infrastructure, including water and sewer systems, for reliable project outcomes.
Explore service
Market
Flood defense. RSP Engineers design stormwater drainage systems, pipelines and pump stations to protect communities and property.
See how we helpTell us about the site, schedule and jurisdiction and we will outline an approach.