Case study · Engineering Robust Industrial Solutions

Site and drainage design for a mobile batch concrete yard in Palmetto, Manatee County

A 1.47-acre industrial infill site in Palmetto was developed as a mobile batch concrete yard with a service shop. Stormwater is held in 1,418 feet of exfiltration trench under the yard rather than in a pond, and the project carries both Manatee County final site plan approval and a Florida DEP permit for its wastewater system.

Location
Palmetto, Florida
Client
a private industrial property owner
RSP role
Civil engineer, site and drainage design and permitting
Status
complete

Client and site identifiers are withheld under a confidentiality agreement; the scope, role and outcomes described are documented in the project record.

Paving, grading and drainage plan for a concrete batching yard showing exfiltration trench runs, 18-inch storm pipe between drainage structures, and the proposed warehouse and office.

What the project was

A 1.47-acre industrial infill site in Palmetto, in Manatee County, was being developed as a mobile batch concrete yard with a service shop. The proposal is an industrial concrete mixer, a cement silo, aggregate stockpiles, a loading pit, and a 6,000 square foot building holding a warehouse and a small office, with the paving, drainage and utilities to support them.

The site is three platted lots in an existing industrial park rather than one parcel, and the county made their consolidation into a single lot a condition of the building permit. RSP was the civil engineer, and carried the site and drainage design through the county's final site plan review and a separate state permit for the wastewater system.

The constraint

A concrete batching yard is a demanding stormwater use on a small site. Washdown, aggregate stockpiles and a loading pit all generate runoff that carries material, and the site is only 64,051 square feet in total, so there is little room for a conventional pond and no margin for a drainage layout that gets in the way of the operation. The yard has to stay a working yard, with room for mixers to turn and for stockpiles to be loaded.

The second constraint was below ground. The design water table sits at elevation 8.00 feet, and the site's drainage therefore had to work in a narrow band: deep enough to store and infiltrate, shallow enough to stay above the water table for most of the year. Hydraulic conductivity was taken from the project's geotechnical report rather than assumed, at 8.27 x 10-4 cubic feet per second per square foot per foot of head.

The third was the sanitary connection. There was no gravity sewer the building could fall to, so wastewater had to be pumped, and a pumped connection to a public system is a state matter in Florida rather than only a county one. That put a Department of Environmental Protection permit on the critical path for a system of modest size.

What the work involved

Stormwater is handled by an exfiltration trench system rather than a pond: 1,418.88 feet of trench, 6.00 feet wide and 6.10 feet deep, giving a storage volume of 12,769.93 cubic feet, laid out in runs along the site's edges and beneath the yard. The design uses a safety factor of two on 150 per cent of the water quality volume, which is the conservative end of the method, and the storage sits under the pavement where it does not take operating area.

The trench network is fed by 18-inch corrugated HDPE pipe between ten drainage structures, at slopes from 0.5 to 0.9 per cent. Every structure carries a pollution-retardant baffle. On a site that disposes of its stormwater into the ground, that detail is what keeps floating material out of the aquifer, and on a concrete yard it is doing real work rather than satisfying a note.

The building sits at a finished floor of 13.50 feet NAVD 88, with the yard graded to fall away from it to the inlets. Cross sections were drawn along four lines so the proposed surface can be read directly against existing grade, which on a site being regraded for truck movement is where the design is actually checked.

For wastewater, the design is a private lift station with approximately 74 linear feet of two-inch force main, connecting to an existing force main in the adjacent street and from there to the Manatee County North Regional Water Reclamation Facility. Water service is a one-inch meter with backflow prevention, and fire coverage was confirmed against an existing hydrant flow tested at 1,125 gallons per minute, within the required distance of the proposed buildings.

A stormwater pollution prevention plan was prepared for the construction phase and for the use itself, covering concrete and masonry washout, stockpile containment and sediment control - the specific risks a batching operation brings rather than a generic erosion control sheet.

Agencies and approvals

Manatee County approved the final site plan on 22 February 2024 under PLN2308-0059, project FSP-23-126. The approval runs across the county's own review sections - planning and zoning, public works development review, floodplain, impact fees and the fire district - and it carries conditions, including the consolidation of the three lots into one before a building permit issues and a certificate of level of service valid to February 2027. The floodplain section recorded no objection, the site lying in flood zone X on panel 12081C0168F.

The Florida Department of Environmental Protection's Southwest District issued permit CS41-0182186-501-DWC/CL on 17 July 2025, authorising construction of the domestic wastewater collection and transmission system under Chapter 403 of the Florida Statutes. The permit runs to 2030 and, as these permits do, requires the Department to clear the system before it is placed into service for anything other than testing.

The outcome

The project holds county site plan approval and a state wastewater construction permit, obtained in that order over about eighteen months.

The site keeps 21,649 square feet of open space, 33.8 per cent of its area, on a use that could easily have paved everything. The stormwater storage that made that possible is underground, in trench rather than in a pond, which is what let a yard this small carry a batching operation and still meet its drainage requirement.

For an owner weighing a similar site, the useful observation is about sequence rather than about drainage. A pumped sanitary connection brings a state agency into a project that otherwise sits entirely with the county, and it is worth establishing early whether a site can fall to gravity sewer, because the answer changes who has to approve the work and how long it takes.

Project facts

  • The site is 1.47 acres of industrial infill, made up of three platted lots the county required to be consolidated into one before a building permit could issue.
  • The development is a mobile batch concrete yard with a service shop: concrete mixer, cement silo, stockpiles, loading pit, warehouse and office.
  • Stormwater is managed by 1,418.88 feet of exfiltration trench with a storage volume of 12,769.93 cubic feet, with a pollution-retardant baffle at every structure.
  • 21,649 square feet of the site, 33.8 per cent, is kept as open space.
  • Wastewater is served by a private lift station with approximately 74 feet of two-inch force main connecting to the Manatee County North Regional Water Reclamation Facility.
  • Manatee County approved the final site plan on 22 February 2024 under PLN2308-0059, project FSP-23-126.
  • The Florida Department of Environmental Protection issued permit CS41-0182186-501-DWC/CL on 17 July 2025 to construct the wastewater collection and transmission system.
  • The site lies in FEMA flood zone X.
Site area
1.47 acres (64,051 sq ft)Approved final site plan set and state permit, 2024 to 2025
Open space
21,649 sq ft (33.8 per cent)Approved final site plan set and state permit, 2024 to 2025
Building
6,000 sq ft warehouse and officeApproved final site plan set and state permit, 2024 to 2025
Finished floor
13.50 ft NAVD 88Approved final site plan set and state permit, 2024 to 2025
Exfiltration trench
1,418.88 ft long, 6.00 ft wide, 6.10 ft deepApproved final site plan set and state permit, 2024 to 2025
Trench storage volume
12,769.93 cu ftApproved final site plan set and state permit, 2024 to 2025
Design water table
Elevation 8.00 ftApproved final site plan set and state permit, 2024 to 2025
Wastewater system
One lift station, about 74 ft of 2-inch force mainApproved final site plan set and state permit, 2024 to 2025
Fire flow
Existing hydrant flow tested at 1,125 gpmApproved final site plan set and state permit, 2024 to 2025
FEMA flood zone
Zone X, panel 12081C0168FApproved final site plan set and state permit, 2024 to 2025
County approval
PLN2308-0059 / FSP-23-126, 22 February 2024Approved final site plan set and state permit, 2024 to 2025
State wastewater permit
FDEP CS41-0182186-501-DWC/CL, 17 July 2025Approved final site plan set and state permit, 2024 to 2025

Questions a similar project raises

Why use an exfiltration trench instead of a retention pond?

A pond takes surface area, and on a site of under an acre and a half being used as a working yard that area is the thing the project is for. Trench puts the same storage underneath the pavement, and in Florida soils it also disposes of the water by infiltration rather than holding it for a slow surface release.

What makes a concrete batching yard harder than an ordinary industrial site?

The operation itself generates runoff that carries material: washdown from mixers, aggregate stockpiles, and a loading pit. The drainage has to be designed on the assumption that what reaches it is not clean rainwater, which is why every structure here carries a pollution-retardant baffle and why the pollution prevention plan addresses washout and stockpile containment specifically.

When does a wastewater connection need a state permit rather than just county approval?

In Florida, constructing a domestic wastewater collection or transmission system needs a permit from the Department of Environmental Protection under Chapter 403, even when the system is small and connects to an existing public facility. A site that can fall to an existing gravity sewer may avoid it; one that has to pump, as this one did, generally cannot.

How does the design water table affect a drainage design like this?

It sets the floor. Storage has to sit above the water table to be available when a storm arrives, and infiltration rates depend on the unsaturated depth beneath the trench. Here the water table is at elevation 8.00 feet and the trench bottom at 3.57 feet, so the design was built around measured conditions from the geotechnical report rather than assumed ones.

What would you want to see before quoting work like this?

A survey, the geotechnical report or at least a sense of groundwater depth, and a clear description of the operation, including where material is stockpiled and washed down. For the sanitary side, whether there is gravity sewer within reach, because that single answer decides whether a state permit is on the critical path.

Civil Engineering Firm

civil

Engineering Land Development

RSP Engineers provides engineering land development services to transform properties effectively.

Explore service
Stormwater Plan

civil

Storm Drainage Design

Expert stormwater design by RSP Engineers ensures effective drainage and management for your project.

Explore service
water and sewer design

civil

Utility Infrastructure Design

RSP Engineers designs utility infrastructure, including water and sewer systems, for reliable project outcomes.

Explore service
Aerial view of a large warehouse and logistics facility surrounded by fields

Market

Engineering Robust Industrial Solutions

Drive your supply chain with RSP’s industrial and logistics engineering. We design efficient fulfillment centers, warehouses and manufacturing plants.

See how we help
Precast concrete drainage structure being set in a trench with corrugated HDPE pipe and an excavator

Market

Engineering for Stormwater Management

Flood defense. RSP Engineers design stormwater drainage systems, pipelines and pump stations to protect communities and property.

See how we help

Have a similar project?

Tell us about the site, schedule and jurisdiction and we will outline an approach.